Oil and natural gas pipelines

Solution and design study regarding the protection of Ø 12″ and Ø 14″ Cartojani crude oil transport pipelines, route located between the Triaj Brazi railway lines and Ghighiului street, Ploieşti city, over a total length of 110 m

Securing the 12” and 14” Cartojani-Ploiești pipelines at the crossing of the Cricovul Dulce stream

Replacement of manifolds and valves at the work point
CONPET S.A. – OIL TERMINAL depot
Constanța

hdd cf triaj brazi 3
hdd 10
colectoare oil terminal

Replacement of a section of the Ø12 3/4’’ Cartojani-Ploiești crude oil pipeline, total length approx. 250 m, Mihai Bravu Street underpass area-LUKOIL

Replacement of the Constanța – C1 pipe section, Ø14”, Cuza Vodă area, approx. 550m

Protection of 24”, 20” and 14” crude oil pipelines at the intersection with the designed roads

lukoil 1
cuza voda
colectoare r1

Protection of 14” and 20” crude oil pipelines

Protection of 6 5/8” and 8 5/8” crude oil pipelines  

Replacement of sections, of approx. 1000 ml in total, of the Ø 10”, 12”, 14” crude oil transport pipes, inside the OMV PETROM – Brazi refinery

newcold 14 si 20
protejare dale
colectoare r1

Securing the undercrossing of the Targul River with the natural gas pipelines DN500 Schitu Golesti – Slatioara and DN500 Schitu Golesti – Stalpeni, in the area of ​​Furnicosi, Arges County

Securing the natural gas pipelines DN500 Filipesti – Razvad and DN400 Filipesti – Moreni, undercrossing of the Cricovul Dulce river, I.L. Caragiale area, Dambovita county

Protection of natural gas transmission pipeline F2 DN 500 Stalpeni Pitesti Sud

furnicosi
caragiale
adp

Bringing the gas delivery pipeline to compliance at SRM Carani

Couponing 3,950 m of gas collector Calacea-Sannicolau Mare degassing

Godevil receiving station DN150 PN63 Nadlac

conducta gaze carani 2
conducta gaze carani 3
nis 1